Why can't I edit or apply this change order?

What the messages mean when a change order can't be edited, submitted or applied.

MessageWhy, and what to do
This change has been submitted. Reset it to draft to make changes …A change in review or approved is frozen so the approval means something. Click Reset to Draft, edit, and submit it again.
This change is closed and kept as an audit record …It was applied or cancelled. Create a new change order.
This change order has nothing to apply …Add a component change, an operation change or a document first.
… references components or operations that are no longer on the bill of materials …The bill of materials changed after this change order was written. Reset it to draft and pick the lines again.
This change order has incomplete changes …A line doesn't say what it changes — a component to add, or a line to remove or update. Complete or delete it.
I can't edit a bill of materials directlyWith the Engineering User role, bills of materials are read-only by design: change them with a change order.